- Development of storage battery container
for MIG 29 aircraft battery.
- Development of booster rocket air-intake
canopy for DRDL (Indian Defence Dept.) for use in AGNI Missile
- Set up fabric wash manufacturing in
1993 in 90 days.
- Set up high-speed powder filling facility
in 1995 in 47 days.
- Set up Pantene moulding and decoration
in 1994-95 in 120 days.
- Set up an integrated mosquito coil plant
in 127 days where benchmark was 270 days.
|
|
|